Infrastructural

  • The Srinagar Development Authority have up-graded the existing infrastructure of Bemina colony like roads, drains, construction of parks etc. Maintenance of allied infrastructure has been entrusted  to line Departments viz; R&B,UEED, PHE and PDD
  • Squatting spaces to Squatters :To provide affordable shopping spaces  to squatters a platform type accommodation has been  constructed at Batmaloo at a cost of Rs 46.84 lakhs which will provide covered squatting space to  91  squatters.
  • Vegetable Mandi at Sidiqabad, Batamaloo:Vegetable Mandi has been constructed  at a cost of Rs 34.00 lakhs at Sidiqabad Batmaloo  under self financing  scheme . 80 vegetable venders who were selling vegetable on roadside have been relocated in this Mandi.
  • Development of Transport Nagar Parimpora ;Goods and Forwarding Agencies  located in various parts of the Srinagar city has been shifted to Parimpora and 75 plots of various sizes  has been allotted on concessional terms. Internal roads, plots and other amenities have been developed at  a cost of  284 lacs.  The agencies have constructed  their premises  and are operational.
  • Development of Bus Stand at Batamaloo and Parimpora.
  • Parking Lots:-SDA is operating parking facilities at Residency Road near SBI, Poloview and Nehrupark. In addition to this a mechanized car parking  is operational at old KMD Adda Lalchowk.Presently two multilevel parking facilities  are being constructed at old SMG and Sheikhbagh Srinagar. The work of construction of these facilities  is in progress. All these multilevel parkings are being constructed under project AMRUT.
  • Urban Transport Regional  Bus Stand  at Panthachowk:Regional  Bus Stand  at Panthachowk has already been  commissioned  for south-bound buses. Jammu  bound  buses  stand has also been proposed here  with tourist Information Centre. (TRC). As  the first phase of the project in pursuance  to Hon’ble High Court decision- the Bus Stand  had to be made operational immediately. Terminal building, passengers shed, stands for matador, auto, sumo  stand were developed in record time and Bus stand was made operational . Other allied activities proposed  in Bus Stand construction informal sector market, on four kanals of land in which 280 spaces have been provided  which has been already auctioned  and  partly allotted. Workshops for heavy vehicles  and light motor vehicles has also been   carved out on 13 kanal of land 121 No. of workshops  have already been allotted. Bus Stand  is operational .
  • Community Halls :The SDA feels that apart  from commercial and developmental activity, it has  social commitment as well many of  the families of Srinagar city are not in a position  to accommodate their ceremonies due to the dearth of space, lower & Middle Income Groups suffer more on this count. To mitigate this problem, the SDA proposed  to construct Community Halls.
  • Community hall has been constructed at Sidiq-abad Batmaloo . The hall is about 2400 sft and supposed to cater all social gatherings in the locality.
  • SDA has also constructed three more community halls at Boatman/EWS Colony Bemina,  Rajuri Kadal and Bemina. The halls are presently operational and in use of general public.
  • COMMUNITY HALL AT GONIKHAN :The SDA has also constructed a Community Hall at Gonikhan (under SADP), of plinth area 1650 sft (double storied). The community hall has been completed and  thrown open  for use of general public .

GROUND FLOOR :-

HALL = 1 NO.

ROOMS= 1 NO.

WASH ROOM = 2 NOS.

IST FLOOR

HALL = 1 NO.

ROOMS= 1 NO.

WASH ROOM = 2 NOS.

STATUS       = COMPLETED

  • Construction of matador/Sumo & Auto Stands at Bemina soura Pandach, Harwan & Rawalpora. Bemina. Matador/Sumo/Auto stand has been developed and made operational  opposite to SKIMS Medical College, Bemina on National High way Bypass & facilities in side the stand is yet to be developed.
    • Soura.A piece of land measuring 2 kanals near by polyclinic Soura has been developed for matador stand. However additional land needs to be identified as 2 kanals is not sufficient for the area.
    • Harwan;Site for Auto/matador/sumo has been developed at Harwan on bank of Dachigam Nallah
  • Multilevel Parking (RAMP TYPE)  at  Sheikh Bagh, Srinagar. (Under Scheme AMRUT) ;SDA is constructing multi level parking (ramp type) at Sheikh Bagh, Srinagar so as to provide parking facilities to General Public and and de-congest the City Centre. Phase-I will involve construction of stilt plus 3 storied parking financed under mission AMRUT and Phase II will have an additional three storied commercial centre. Latter will be self-financed by SDA. Work  for Phase I is under progress and  anticipated time of completion is March,2021.

The details of the project are as under:

—Total land     =  13.00 kanals

—Total floors    =  Ground+ 6 (3 floors commercial)

—Four wheeler parking    =  430  (Cars)

—Two Wheelers     =  50

Source of funding  =  Rs. 25 Cr  under AMRUT + Self Financing

—An Amount of Rs. 25 Cr. stands approved under AMRUT for the project(for parking only).

—Date of laying foundation stone =  04-01-2017

—Date of start of work                   = 07- 04-2017.

—Date of completion{expected}  = March 2021

—Present status of work  =     Work in progress

  • Multilevel Parking At old SMG behind press enclave. (Under Scheme AMRUT) ; SDA is constructing a multi-level parking at Old SMG Premises, lalchowk,Srinagar so as to provide parking facilities to General Public and and de-congest the City Centre.

Salient features of the Project.

—Total land     =  13.01 kanals

—Total floors  =  Ground+ 6 (3 floors commercial)

—Four wheeler parking    =  467 (cars)

—Two Wheelers        =  130

—Source of funding  =  Rs. 30 Cr  under AMRUT + Self Financing

—Date of laying foundation stone=  04-01-2017

—Date of start of work    = 07- 04-2017.

—Date of completion{expected}= December 2020

  To fill the gap of  Financing/Commercial Space has been  carved out.

An amount of Rs. 30.00 crores approved under AMRUT(for parking only).

Present Status of work = Work in progress.

  • Multilevel Commercial cum Parking Complex at Old KMD Adda :Srinagar development Authority has hand over a patch of land measuring 10.50 kanals to ERA for construction of multilevel Hydraulically driven parking lot. The ERA formulated detailed project report to the tune of Rs 30.00 crores. The parking lot  accommodates 286 four wheelers. The work on the project has been completed and the parking is operational.